News » Up To £20m » Piles in for Newark wind farm » published 3 Aug 2016

Piles in for Newark wind farm

Aarsleff Ground Engineering has completed the foundations contract for the Newark wind farm in Hawton, Newark-on-Trent.

Aarsleff's Junttan PM20 rig was fitted with a five-tonne accelerated hammer. Above: Aarsleff's Junttan PM20 rig was fitted with a five-tonne accelerated hammer.

Main contractor RG Carter Civil Engineering has subcontracted to Aarsleff the installation of 54 piles for each of the three turbines to be erected, meaning 162 piles in total.

Piles installed will be 338mm diameter open-ended steel tubes, with an anticipated pile length ranging from 18 metres to 24 metres, founding in sandstone.

The work was carried out in July 2016 with a Junttan PM20 rig, fitted with a five-tonne accelerated hammer.

The three turbines are expected to generate enough energy to power the equivalent of 5,400 homes.

 

 

MPU

Download our free construction news iPhone / iPad app. Sign up to our FREE email newsletters or subscribe to our RSS feed for regular updates on the latest Construction News, Plant News, Contract News & Supplier News. The Construction Index also provides the latest Construction Tenders, Construction Market Data & Construction Law Commentary all FREE.

This article was published on 3 Aug 2016 (last updated on 3 Aug 2016).