200 PFI contracts facing expiry: consultants, fill ya boots!

1 Mar 22 Construction consultants, lawyers and surveyors are in for a field day – which should already have started – helping public sector clients plan the expiry of private finance initiative (PFI) contracts.

PFI was a procurement tool popular in the 1990s based on the buy now/pay later principal. Construction companies teamed up with investors to build roads, hospitals and other public infrastructure at little or no immediate cost to the public purse. In return, they would be paid for the next 25 or 30 years to maintain the asset, shouldering liability for any defects in their construction work.

Even the Treasury was eventually forced to admit that it was an expensive way to buy infrastructure and had all been a horrible mistake – but it took until October 2018 for the government (chancellor Philip Hammond) to announce that it would no longer use PFI.

Now we are faced with a new problem: what to do when those long-term PFI contracts expire?

Over the next five years, 72 PFI contracts are coming to an end in England. Some £3.9bn of assets will revert to public sector ownership.

Over the next 10 years, more than 200 PFI projects, representing assets worth over £12bn, are set to expire

A report by the National Audit Office in June 2020,  Managing PFI assets and services as contracts end, found that public sector bodies risk underestimating the time, resources and complexity involved in managing the end of PFI contracts. It said that there was a danger that important infrastructure could return to the public sector in an unsatisfactory condition and services could be disrupted.

While authorities will want to ensure they receive assets in the best possible condition at contract expiry, PFI providers have an incentive to limit spending on maintenance and improvement work in the final years of contracts, the NAO warned, as savings can be used to pay higher returns to investors. A survey of public authorities managing PFI contracts found that a third of them expect to have formal legal disputes over the end of contracts.

Good news for construction lawyers.

The same survey found that 55% recognise they need more knowledge on asset condition and 60% recognise they will need to recruit external consultants to help with contract expiry.

Good news for surveyors and consultants.

Gareth Davies, the head of the NAO, warned: “With the bulk of PFI contracts expiring from 2025 onwards, there is still time for government to make changes that will help public sector bodies to exit from contracts successfully. If government does not provide strategic support and public bodies do not prepare sufficiently, there is a significant risk that vital infrastructure such as schools and hospitals will not be returned to the public sector in the right condition and taxpayers and service users will bear the brunt of additional costs and service disruption.”

That was June 2020. It has taken more than 18 months but the IPA has now finally produced some guidance.

This week the IPA has published Preparing for PFI Contract Expiry as guidance for public bodies faced with PFI contracts coming to and end

Related Information

It spells out the risks starkly, and recommends at least seven years is allocated to planning for the expiry of PFI contracts.

The guidance says: “All PFI contracts are based on the transfer of construction and operational risk to the private sector and are structured around outputs not methods of delivery, so the authority may have spent many years distanced from how the service is being delivered. As a result:

  • There will often be a lack of information available to the authority, and the contractual right to information may be restricted or ambiguous.
  • There may be a lack of people, skills and experience to manage expiry.
  • There may be adversarial relationships between the PFI parties and a lack of effective contract management from both sides.
  • There may be a lack of detail or practicality within the contract around the conditions and processes for expiry and handback.
  • There may be a limited, or no, horizon beyond the end date of the PFI contract for key aspects to be considered, such as residual life of assets or future operational costs.
  • Follow-on services must be in place by the expiry dates to ensure continuity of services. Contractual rights to extend are unusual and were only included in early contracts.”

Public sector bodies are advised to commission early condition surveys, to ensure that asset condition and asset information at handback meet all contractual requirements, and to get their lawyers to trawl through the detail of contracts.

The IPA warns that the public sector has to get this right because there may be no recourse later. “PFI Co may be a shell entity after contract end, meaning there is no simple corporate recourse to existing funds to address issues that may arise after expiry.”

However you cut it, the same sort of people that made millions creating the Frankenstein’s monster that was PFI are exactly the same sort of people who are going to be paid even more millions to untangle the whole unseemly mess.

IPA advice Fundamentals of a successful PFI contract expiry

Approach to expiry

  • Recognise the complexity of managing PFI contract expiry and take the lead, rather than being led by the PFI Co.
  • Develop a clear plan for expiry and do so as early as possible – the IPA recommends this planning starts at least seven years before expiry.
  • Seek and obtain senior level buy-in. This is essential given the nature of the decisions that may be required.
  • Organise and manage the expiry process as a project.
  • Commit appropriate additional expert resources – the expiry process will require specialist commercial, technical and legal support.

Contract awareness and management

  • Understand your PFI contract fully and assess the adequacy and practicality of the exit and handover provisions.
  • Ensure good operational contract management is in place enabled by appropriately experienced and skilled staff.

Relationship management

  • Look to build effective relationships and governance, as the expiry process will create new dynamics and pressures.
  • Tackle the awkward and frictional aspects of expiry early and seek to resolve ambiguity.
  • Aim for agreed expiry processes with the PFI Co based on a single shared set of documentation.

Assets

  • Understand the assets and the systems required to maintain and operate them.
  • Be proactive and take early actions to ensure asset condition is as required at handover.

Commercial approach

  • Understand the commercial issues.
  • Establish your commercial goals.
  • Factor in the goals of the PFI Co.
  • Identify and deploy your negotiating leverage.

Future services

  • Understand the requirements for assets and services after the PFI contract ends and begin planning their delivery.
  • Understand and plan for people-related issues.
  • Allow sufficient time for the future services provision to be fully functional at the point of PFI contract expiry.