Construction News

Fri April 26 2024

Related Information

Firm fined for botched TK Maxx concrete pour

11 Jul 11 A court case on Friday (8 July 2011) has highlighted the importance of temporary works engineers.

A Staffordshire-based interior design company has been fined after two men were injured while carrying out refurbishment work at a TK Maxx outlet in Hounslow.

Three men were pouring concrete to fill in an opening in the first floor of the retail unit, left following the removal of stairs and an escalator.

The Old Bailey heard that on 21 September 2006 the men had only just begun to pour the concrete when the temporary propping erected to support the underside of the decking, installed within the opening, collapsed. This caused the men to fall more than 4.8 metres to the floor below.

All three men were taken to hospital, one with a dislocated shoulder, another had a fractured pelvis and elbow, the third worker was unhurt.

Key to the case was that no temporary works engineer had been appointed.

Bridgford Interiors Limited, of Fradley Park, Lichfield, Staffordshire pleaded guilty to breaching section 3(1) of the Health and Safety at Work etc Act 1974. The company was fined £25,000 and ordered to pay costs of £23,392.

HSE inspector Viv Neaverson said: "This prosecution arises as a result of Bridgford's failing in their duty as the company responsible for the temporary work. Whilst they had appointed a structural engineering company to execute the permanent works, they had not appointed a temporary works engineer and, as such, this duty fell to them."

Got a story? Email news@theconstructionindex.co.uk

MPU
MPU

Click here to view latest construction news »