Height safety failings cause broken neck

22 Jun 21 A Chesterfield construction company has been fined £8,000 after a subcontractor fell from roof joists to a concrete floor below, breaking his neck.

A joist failed during construction of the extension
A joist failed during construction of the extension

The incident happened during work on a domestic extension at Mona Road, West Bridgford, Nottingham.

Bobby Oldham Construction Limited was contracted to complete an extension to the rear of the property, which contained a skylight and wooden joists. 

Nottingham Magistrates’ Court heard that, on 19th June 2019, work had progressed to the point where roof joists were being attached. The joists were accessed using a ladder, which then led to an unprotected trestle platform.

A subcontractor was sat astride one of the joists when it gave way, causing him to fall. He landed on the concrete floor below sustaining serious injuries including brain trauma and a broken neck.

Related Information

An investigation by the Health & Safety Executive (HSE) found that had the company properly considered the risks associated with this type of work, and planned the work at height more carefully the incident could have been easily avoided. The trestle platforms were missing suitable edge protection, and there was an absence of other suitable fall mitigation measures such as airbags. The work was not supervised, which would have identified the unsafe working methods, which could then be challenged by the company.

Bobby Oldham Construction Limited (BOCL) of Market Street, Staveley, Chesterfield, Derbyshire pleaded guilty of breaching Regulation 4(1) of the Work at Height Regulations 2005. It was fined £8,000 and ordered to pay costs of £3,515.

HSE inspector Phill Gratton said after the hearing: “This was a tragic and wholly avoidable incident, caused by the failure of the host company to implement safe systems of work, and failure to ensure that work at height was properly planned and appropriately supervised.

“This risk was further amplified by the company’s failure to undertake a number of simple safety measures including conducting pre-start checks on the training of workers, planning work to ensure that working methods were safe, and supervision to ensure that dangerous working methods could be observed and challenged.”