Construction News

Wed May 08 2024

Related Information

Covid compliance adds six months and at least £500m to Hinkley Point C

27 Jan 21 EDF Energy has recalculated the costs of the Hinkley Point C nuclear reactor that it is building in Somerset in the wake of Covid-19 restrictions.

Hinkley Point C  managing director Stuart Crooks
Hinkley Point C managing director Stuart Crooks

Contractors on Hinkley Point C have ben working since March 2020 with reduced staff numbers and with routines restricted through compliance with new site operating procedures, including social distancing.

Despite this, they hit 18 out of their 20 miletsones in 2020 and the other two were “not far behind” said, HPC managing director Stuart Crooks.

“That’s a considerable achievement with fewer people on site,” he said.

However, a detailed review of schedule and cost has concluded that the start of electricity generation from Unit 1 is now expected in June 2026, rather than the end of 2025 as initially announced in 2016.

The project completion costs are now estimated in the range of £22bn to 23bn, as opposed to the revised window of £21.5bn and £22.5bn (at 2015 prices) announced in September 2019. [Construction costs rise 10% at Hinkley Point C]

As a consequence, the projected rate of return for the French state-owned energy company is now estimated at between 7.1% and 7.2%, rather than the previous 7.6% to 7.8%.

Stuart Crooks said that three months of scheduled time had been lost in 2020 and it was estimated that another three months could be lost in 2021 “assuming that conditions allow us to ramp back up the resources after Easter,” he said.

He added: It is important to remember that this is a health crisis not an issue with construction. The fundamentals of this project remain good.”

Got a story? Email news@theconstructionindex.co.uk

MPU
MPU

Click here to view latest construction news »