River wall takes shape for Shoreham housing

30 Aug 19 The first stages of a flood defence project to enable housing regeneration are under way in West Sussex, with the installation of piles for a new river wall.

The Soilmec SF50 CFA drilling rig put in 274 concrete piles
The Soilmec SF50 CFA drilling rig put in 274 concrete piles

Central Piling was appointed by civil and marine engineering contractor JT Mackley & Co to install 274 concrete piles as part of the enabling works for Southern Housing Group’s Free Wharf development in Shoreham-by-Sea.

Southern Housing plans to build 540 new homes on a former aggregate-processing site on the western arm of Shoreham Harbour but building work cannot start until a new river wall has been built to replace the existing sheet piled wall.

Wates Residential, which is leading the £5.5m enabling works contract for Southern Housing, appointed Mackley to carry out the river wall element of the works. This includes the construction of a new reinforced concrete structure that will eventually form both the new river wall and a podium slab for a public realm area, and will also tie into an underground car park beneath the apartments.

The concrete structure is founded on a line of bearing piles designed and installed by Central Piling.

Central Piling arrived on site in June 2019, and completed the work in 25 days using a Soilmec SF50 continuous flight auger drilling rig. The piles are 350mm and 450mm in diameter, and vary in depth from 11.6 metres to 19.5 metres. They have been designed to cope with vertical loads ranging from 300kN to 900kN, and lateral loads of up to 100kN.

Related Information

The piles were installed through made ground into the underlying chalk, with Central Piling making use of an existing concrete slab to support the drilling rig – something that had been specified by Wates at the tender stage.

Wates Residential undertook a site investigation and assessment to ensure the existing slab would suitable as a piling platform. The contractor then cored through the slab in all the pile locations to enable the piles to be installed, and also probed down ahead of the piling to make sure there were no obstructions.

The enabling works – including the river wall – are due to finish in late 2019. Construction of the new homes will require a further 2,000+ piles to be installed for the building foundations.